Modernisation of rotor hydraulic lift pump of steam turbine unit K-1200-6.8/50

https://doi.org/10.26583/gns-2024-03-05

EDN: NICFCO

Abstract

Equipment of foreign manufacturers was widely used in the Russian industry in the recent past.
At the same time technical support for the operation of such complex equipment is currently significantly hampered or non-existent under the pressure of sanctions and system restrictions imposed on Russia. The Novovoronezh NPP staff is confronting successfully such challenges by developing technical solutions that enable the continued efficient operation of imported equipment under the new reality. One of the many examples of the efforts of the Novovoronezh NPP staff to ensure Russia's economic safety and technological sovereignty is given in this article. During operation of power units with VVER-1200 reactors, failures in operation of turbine unit rotor hydraulic lift pumps of Allweiler GmbH (Germany) were identified. As part of the programme of import substitution and improvement of equipment reliability on the basis of available documentation and comparative analysis of operation modes of turbine unit rotor hydraulic lift pumps pumps at Novovoronezh and Leningrad NPPs, the technology of turbine unit rotor hydraulic lift pumps repair with modernisation of internals by means of installation of bronze bushing and observance of precise clearances of pump internals is developed. Improved circuit solutions for the system of hydrostatic lifting of rotors are proposed which exclude damage to the turbine unit rotor hydraulic lift pumps during operation of the power unit at capacity and during scheduled preventive maintenance. The modernisation of equipment manufactured in Germany and its successful operation at Novovoronezh NPP is a vivid example of a scientifically sound technical response to the sanctions pressure of foreign countries and can be extended to other Russian enterprises as a positive practice.

About the Authors

V. P. Povarov
Branch of JSC Concern Rosenergoatom Novovoronezh Nuclear Power Plant (Novovoronezh NPP)
Russian Federation

Dr. Sci. (Engin.), Head 



D. E. Usachev
Branch of JSC Concern Rosenergoatom Novovoronezh Nuclear Power Plant (Novovoronezh NPP)
Russian Federation

Head of the 4th stage turbine shop



A. P. Shchukin
Branch of JSC Concern Rosenergoatom Novovoronezh Nuclear Power Plant (Novovoronezh NPP)

Head of the Experimental and Demonstration Engineering Centre of Decommission­ing



V. A. Vorotnikov
Branch of JSC Concern Rosenergoatom Novovoronezh Nuclear Power Plant (Novovoronezh NPP)
Russian Federation

Head of the Centralised Repair Shop



A. A. Lotarev
Branch of JSC Concern Rosenergoatom Novovoronezh Nuclear Power Plant (Novovoronezh NPP)
Russian Federation

leading engineer, Centralised Repair Shop



Review

For citations:


Povarov V.P., Usachev D.E., Shchukin A.P., Vorotnikov V.A., Lotarev A.A. Modernisation of rotor hydraulic lift pump of steam turbine unit K-1200-6.8/50. Nuclear Safety. 2024;14(3):56-61. (In Russ.) https://doi.org/10.26583/gns-2024-03-05. EDN: NICFCO

Views: 106


Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 License.


ISSN 2305-414X (Print)
ISSN 2499-9733 (Online)